The MGT Biomass Power Plant on Teesside is a ground-breaking UK project – the largest of its kind in the world and one Logic-i is proud to have been part of. We played an integral role in the project management team, delivering high-quality commercial, planning and project controls on behalf of the Atlantic Projects Company (APC).
Our contribution ensured that APC maintained tight financial and operational control throughout the Boiler installation. Although extremely challenging – this was the first time anyone had attempted to build an innovative, 299MWe thermal combustion power plant at such a scale – we helped deliver a safe and successful installation.
MGT began construction in August 2016, with full commissioning planned for 2020 and commercial operations coming on stream in 2021. We’re happy to have helped the project meet its deadlines and it’s been great to be involved in such an innovative and important project.